SAC meeting September 30 - October 1, 2004 Cambridge (MIT)

Dates and locations:

Sep 30 (Thu) - MIT Building 37, Room 252, Marlar Lounge

Oct 1 (Fri) MIT Building 26, Room 110, Compton Room

 

AGENDA (TXT)

Instrument Priorities Survey results

Minutes (PDF)

Technical manager's report, A. Uomoto [ PDF SXW ]

Report from Las Campanas, M. Phillips [ PDF | PPT ]

Report from Las Campanas, M. Roth [ PDF | PPT ]

Staffing update report, A. Uomoto [ PDF | PPT ]

Future instrumentation, A. Uomoto [ PDF PPT ]

Instrument priorities poll, A. Uomoto [ PDF PPT ] The ranked list is in the Instrument Priority Survey

Interrupt and TOO observing (discussion only; no slides. A. Dressler)

CorMASS, K. Luhman [ PDF | PPT ]

FIRE, or the IR echellette, R. Simcoe [ PDF PPT ]

GLAO update, A. Athey [ PDF | PPT ]

GLAO movie, A. Athey [ MPG ]

F/5 wide field corrector, A. Szentgyorgyi [ PDF PPT ]

Megacam status report, B. McLeod [ PDF PPT ]

MMIRS status report, B. McLeod [ PDF PPT ]

Mirror coatings and cleaning, F. Perez [ PDF PPS ]

MagE, S. Burles [ PDF PPT ]

MagE specs and throughput estimates, S. Burles [ PDF ]

PISCO, C. Stubbs [ PDF PPT ]

LDSS, J. Mulchaey [ PDF | PPT ]

IMACS & GISMO, A. Dressler [ PDF PPT ]

Improving cost effectiveness, A. Uomoto [ PDF | PPT ]

Swift and GRB observations, H.-W. Chen [ PDF PPT ]

Facility instrument policy compliance: see section 10 of the technical manager's report, A. Uomoto

User instrument policy, A. Uomoto [ PDF PPT ]